Monday, March 29, 2010

Another weekend of digging

Not too much progress this weekend. I got the rocks out of the hole from last weekend, and dug some more.

I've put the rocks out on the curb to get rid of them. Craig's List seems like a good way to get people to come haul them off. They use them as landscape rocks, I assume.



After getting the rocks out, which required using the jackhammer to break several into smaller more manageable pieces, the rest of the time was just digging, and moving the dirt out of the way.



There is a solid layer of rock about 20 inches down. I expect several weeks of just digging, to get the soil cleaned up, removing rocks and mixing in compost.

Thursday, March 18, 2010

Starting The Box

The next area to work on is a planter/bed area just off the porch. It was dominated by a large cedar tree, which we had cut down. So now we have a stump to remove. I've started by clearing off all the previous plantings, and removing the little stone edging around it.

Here's what the tree looked like before it was removed.



And that leaves me with the following to work on:





And in particular the stump.



I expect to dig around this until it's isolated and then break it up into smaller pieces to get it out.

After a couple of days of digging, I have exposed a couple of big rocks in a 5 foot by 7 foot hole. I managed to pry the small one out and put it on the stump to get it out of the way. I pried another larger one up on top of another. I may need to break these into smaller chunks to make them manageable.



Under these rocks, about 21 inches from ground level, it appears I have a solid, smooth unbroken layer of rock, so that's about as deep as I can go.

After this work, it has rained, so I can't really do anything more until it dries up. And Spring Break is over, so it's back to digging only on the weekends.

Last work on the Bamboo Grove

I'm off work on Spring Break, and it's stopped raining for a few days, so I was able to go out and shovel more dirt into the bamboo grove. This should fill it back in. The wall is done, and other than needing to bring in more dirt as things settle, the Bamboo Grove is done. All the dirt has been dug up, the rock removed and the dirt quality improved. As the dirt settles, I will probably need to bring in a bit more.




Sunday, March 7, 2010

Finishing the Bamboo Grove Wall

I was able to get back to work on the Bamboo grove -- the Cedar Allergies are gone, it's above freezing, and there was a break in the rain. It's been since like November that I was working on this. So first, we have to establish where we were. We need to put a concrete wall, with rock topping under the back fence. We will use the jackhammer to go straight down under the fence. That will provide one side of the concrete wall.




It turned out to be easier to just use the pick axe (really a grubbing hoe) to even it up under the fence. Then it's the standard approach. Staple black plastic on the fence, to provide a water proof barrier on one side. Use a high pressure water hose to spray the bedrock down, to get it as clean as we can. Then put up a masonite form for the other side, keeping them separated by a 1x4 piece of wood. I have all these bags that used to hold compost that I've filled with rock to use as sandbags to keep the forms in place. Then mix up the concrete (I use just 80 pound bags of ready-mix) and shovel it in, removing the 1x4's as each section is filled with concrete. After a couple days, remove the forms.



Another day of mixing up just mortar and using it to put cut limestone rocks on the top, to make it look better than just concrete. Let that dry and we are done.




Now we are ready to fill the space in with dirt. We have a big pile in the bamboo grove, but given the amount of rock we have taken out, we will need to bring in more.

March 6 and 7, 2010

I spread the dirt pile around and filled in much of the area, but still need more for the complete area. I've been mixing in all the leaves from last fall as I shovel the dirt back, so there should be some organic matter mixed with the soil. It's a very heavy clay soil and still very wet. It was marginally reasonable to shovel it in this condition -- it seemed with every shovel full, more stuck to the shovel than was moved. But the forecast says more rain tonight and tomorrow, so this is the best opportunity in a while.

Winter 2010

It's been really wet this winter. And cold. So not much done outside during this time.

I put up a ramp for the dog, to get down from the back porch to the ground. The dog is getting very old (16 or 17 years old) and has developed a limp. She is now having difficulty going down the stairs. So this should make it easier for her. I made it out of two 12 foot 2x4's from Home Depot, plus some leftover siding/plywood from the attic. I ripped the plywood into 18 inch pieces and screwed it down to the 2x4's. Then to keep her from jumping off the side, I put a short piece of siding on the side, Since I had the siding and screws, the total cost was just the $9 for the two 2x4's.




March 2, 2010

The other activity was to trim the trees. The trees are so thick, especially in the front, that the grass is dieing (or is dead). We went with Crawford's Tree Service (http://www.happiertrees.com). $750 to have most of the trees trimmed. Below is the live oak in the front (named Fuzzy), before and after.


Tuesday, December 8, 2009

First half of concrete wall

Now that the digging is done, the next step is the concrete separating wall. We are going to put in a concrete wall, down to bedrock, to keep the bamboo in (or out) to this specific area. To be a bit more attractive, we put a rock edge along the top.

So the first problem is to get the rock. Whittlesey Landscape in Round Rock has some 4x4 rock for 7 cents a pound. I got 520 pounds for $39.40 (27 November 2009). This should be 50 linear feet or more. In the photo below, I just laid them at the base of the fence to get an idea of how much length I have, and what it will look like.



In addition, I will need concrete and mortar mix -- the concrete for the wall and the mortar mix to attach the rocks to the top. The process is fairly simple. I put a black plastic sheet on the "dirt" side, to keep the concrete from mixing with the dirt. I use 1x4's to keep the forms 4 inches away from the dirt, and then put the forms on the outside. For the forms, I just bought a 4x8 sheet of masonite from Home Depot ($12) and cut it down to 3 16-inch tall pieces. I use the plastic bags of bad dirt as sandbags, to hold the form in place. Then I mix up a bag of concrete and shovel it into the space between the plastic on the far side and the form on this side. As I shovel the concrete in, I can pull out the 1x4's -- they are just there to keep the form from collapsing next to the black plastic.




It's a dirty messy job. Part of this is because the weather was sort of wet, but also just the water to clean the bedrock, and to mix the concrete.

Once the concrete is firm, the forms can be removed (and re-used for the next section). The black plastic can be trimmed off (but you can't get it out from behind the wall -- that's intentional; it should help seal the wall from anything coming thru it). Mix up the mortar mix and use it to put on the top edge of rock.



In the photo above, I don't have all the rocks attached yet, but the part that is done looks good. I have to finish all the way around to join up with the first separating wall, and close the wall around the bamboo grove.

But there will be a delay -- I seem to have acquired "tennis elbow", and the doctor says to lay off this work until I get better. I would still hope to be able to finish by the end of the year, but there is no rush. And with the wet winter weather, it's difficult to work. And cedar allergy season is about to start.

Thursday, November 26, 2009

Final digging in the Bamboo Grove

It's still pretty wet out there, but seems to have dried up enough to work. I think that the French drain is actually working, and over the past week or more, the water has worked its way into the French drain, down the pipe to the retention pond and then out the drainage holes into the trench from digging and down the
yard to the corner.

But despite that, and the dirt being wet, I dug out the last part.



This gets me all the way from the drainage pond to the fence corner and then back to the retaining wall that should seal the bamboo grove off from the yard.



The next step will be to pour a concrete wall under the fence and put rock on the top to match the retaining wall. This will prevent the bamboo from escaping under the fence, and confine it completely to this one area of the back yard.

I've started collecting together the rocks to go on top of the cement wall. I need to get some "forms" to outline the wall. Previously, I just used some 2 foot by 8 foot pieces of masonite. It's light weight and smooth on one side, and flexible, so it's easy to work with. And I need concrete mix. I'll need to figure out how much.


.

Tuesday, November 24, 2009

More Radiant Barrier

The back yard is still too wet to dig, so taking the opportunity to finish the attic today. The first step was to finish putting the radiant barrier over the finished part of the attic over the garage.



Next we used the last roll of the radiant barrier material to run down the area over the living room. The living room has a vaulted ceiling, so the framing of it is a bit more complex than for the rest of the attic.



When we put the radiant barrier over the living room, we had to remove the light that we had hanging there. So we installed a fixed fluorescent light fixture on the wall between the carpeted cat walk (on the right in the photo below) and the area over the living room.



And finally, we put a shelf in the area over the utility room (the hot water heater and the vent over the stove top) to put the telephone equipment (wiring, plugs, tools, outlets). That gets the box up off the floor and out of the way.



I think this finishes almost everything in the attic. I guess I need to go back over the Energy Audit and see if anything else comes up.

Monday, November 23, 2009

Radiant Barrier for the Attic

I'm off for the Thanksgiving holiday. It's much too wet outside to dig -- standing water in the trench I've been working on, so it was up in the attic to try to finish the area over the garage.

The Energy Audit had identified the area over the garage as having no insulation and no radiant barrier. I last worked on this September 20, and put down a layer of 6 inches of fiber glass insulation between the floor joists. This time I installed radiant barrier on the inside of the roof, and then put R-30 fiber glass rolls down on top of the previous insulation, running the new rolls perpendicular to the old insulation.




I put the radiant barrier up first and then filled in with the insulation. That should finish off the unfinished part of the attic, over the garage. I am left with the finished part over the garage, which needs a radiant barrier, and some other random places which also need radiant barrier. I needed to get more over the material. The radiant barrier comes in rolls of only 4 feet by 25 feet, so I needed another 4 rolls for these areas. These were about $184 at Home Depot.

I'll need a step ladder or something to install it over the finished floor part of the attic.




That should be tomorrow's work.

Monday, November 16, 2009

Into the final stretch

October and November 2009

It's been dry now a couple of weekends and I've been able to get out there and dig. I've turned the corner of the fence and started digging along the back stretch. The bedrock is somewhat less smooth here. Part of it is the utility trench. When the development was put in, all the utilities -- electrical, telephone, and cable -- were put underground. Apparently code says they should be 16 to 18 inches below ground level. Of course, as we've seen, bedrock is only 4 to 8 inches below ground level.

So they brought in a rock saw and cut a trench into the rock and put the cables in that. The chewed up rock was just dumped along side the trench and then dirt put over the whole bunch. I take off the dirt, then I'm putting the rock debris into compost and mulch plastic bags. In the short term I will use them like sandbags to hold the cement forms when I pour the cement wall, and then I'll haul them off.




I actually dug deep enough to find the cables near the corner. In the actual corner the rock formation is very different. It goes very deep in dirt. I wasn't able to find the underlying rock. But I did uncover the cables. They are in a big (probably 4 inch diameter) grey PVC pipe. Which is good, since it probably would not be good for me to break into a high voltage power line.



Having gone as deep as I figured I have any reason going, I continued on along the fence. Pretty standard digging, except for a strange notch in the bedrock. It's too rectangular to be natural, so I guess someone did this when the trench was put in.



All this digging has produces a big pile of dirt, but I think I'm just a couple (digging) days from finishing the excavation, so I should have enough room. Once I get the wall poured, I can put it all back (and more!).




I used some of the ground up limestone from when they cut the trench to cover over the electrical pipe, and fill in the corner to a level.



So, a bit more digging, then I can start framing for the concrete work. And I need to get rocks to put on top of the concrete, to make it a bit more "natural", so it will match the other exposed rock walls. I may be able to finish before Christmas. Depending on the weather, of course.